A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?
A Chief Executive Officer (CEO) has approached a project team member to request a project change. Which of the following would be the BEST step for the project manager to take to prevent scope creep?
A team member has completed a project task. Which of the following is the FASTEST method to communicate the task completion?
Which of the following is the MOST appropriate communication method for a highly confidential message to a Multilanguage global project team?
Which of the following is a characteristic of a project?
Which of the following describes some of the features of the Agile methodology?
An organization has determined that all projects must use a remote dashboard to allow portfolio management. Which of the following would enforce this directive?
Which of the following defines the minimum level of engagement of a stakeholder?
A project team has completed a major deliverable earlier than planned and wants to deliver it for testing. The team lead sends an email providing notice of task completion to the project manager.
Which of the following describes how the project manager can increase the likelihood that the deliverable moves to testing?
An organization needs a vendor to provide a solution. The organization can only describe its goals but not how to accomplish the work.
Which of the following types of procurement should be used?
A project team has failed to deliver on changes the project manager outlined on a call two weeks ago. The project team members indicate they did not remember the contents on the call. Which of the following should the project manager do FIRST to improve the level of awareness of changes to the project schedule?
At a project kickoff meeting, several team members acted unprofessionally. The project manager would like to set expectations for team interaction. Which of the following would BEST accomplish this?
A project manager has been experiencing resistance from a group of stakeholders.
With which of the following should the project manager consult to reduce friction going forward?
Which of the following captures unforeseen activities throughout the project that need attention and resolution?
A quality auditor finds suspicious code during a software test. For which of the following could this be a trigger?
A company is in the process of combining the human resources and marketing departments. Which of the following describes this change?
New requirements were introduced during the execution phase of a project, and the team believes this will impact the project cost but not the timely completion of project deliverables.
Which of the following is the BEST way for the PM to validate the assessment?
A project manager wants to ensure that a detailed overview of a new kitchen fits the client’s standards. Which of the following will the project manager MOST likely work to accomplish?
A change is being implemented on a project, and while in testing, it becomes clear that the change cannot be finalized due to the severe impact it would have on other critical systems. Which of the following should the team consult to determine which actions to take?
Which of the following conflict resolution techniques relies on establishing areas of agreement rather than disagreement?
A key stakeholder asks the project manager for additional features. Which of the following documents should the project manager refer to before responding to this request?
A senior developer abruptly resigned without notice. Because of the senior developer’s expertise, the active task workload was substantial.
This would likely impact the project’s: (Choose two.)
During the planning phase of a construction project, the project team discovers the site is the nesting area of rare birds, and construction could disrupt the birds’ patterns. Lobbyists would like the team to move the project down the road.
Which of the following constraint and influencer types are involved in this scenario?
Which of the following risk strategies prevents a risk from impacting a project?
Which of the following information does the project risk register typically contain?
Which of the following features describe a projectized organization? (Choose two.)
An active project has a CPI of 0.92. Which of the following can be determined?
A project encountered a problem and reached a milestone. In which of the following documents will the stakeholders MOST likely find information on these events?
Which of the following are the BEST risk analysis tools to determine a project’s risk level? (Choose two.)
A project team completed a brainstorming activity to determine potential issues with a project. Which of the following activities should the project team do NEXT?
A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project manager use FIRST to relay this information?
A project manager is procuring new equipment from a vendor. The vendor requires a physical signature on all purchase orders. Which of the following should the project manager do to order the equipment quickly? (Choose two.)
A customer has stated that meeting the project schedule and milestones takes priority and is, therefore, willing to spend additional funds to sustain operations. The project team must ensure completion of the:
Which of the following documents ensures two parties do not share contractually binding information?
Due to a lack of adherence to the risk response plan, there are numerous safety concerns within the scope of a building project.
Which of the following MOST likely explains this issue?
While developing a project schedule, the project manager is attempting to sequence the following tasks:
Which of the following is the correct sequence for the above tasks?
Tasks B and D start after Task A is completed. Task C starts after Tasks B and D are completed. task E starts after Task D is completed. Task H starts after task B is completed. Task G starts after Tasks C and H are completed. Task F starts after Task E is completed.
Following are the durations of all tasks:
Which of the following tasks are on the critical path?
A new contractor joining the project team is an example of:
Which of the following represents additional unauthorized requirements from the client?
Which of the following documents should be used FIRST when addressing a vendor that is not complying with the project deliverables?
A project sponsor, project manager, and project facilitator are drafting a project charter. The final contents of this documentation will be presented to the project steering committee for review and approval. The following sections are currently documented:
1. Project description
2. Draft project timeline and schedule
3. Rough milestones
4. Draft project budget
5. Draft resources required
6. High-level risk review
Which of the following sections should be included in this document?
A contract review meeting has been scheduled with a non-performing vendor. The project manager has been asked to provide recommendations for continuous service improvements and removal of the vendor. Which of the following documents should the project manager review BEFORE the meeting?
A project manager is overseeing a multinational project, and team leaders from numerous countries indicate the team members have low morale.
Which of the following is the MOST likely reason the project manager would be unaware of the team member’s decreased morale?
A primary work location is unsafe due to a gas leak. The project manager has implemented the business continuity plan and authorized relocation to an alternate site.
Which of the following should be notified?
Which of the following describes KPIs?
A vendor advises the project manager that a key component of the project is no longer available and recommends a higher-cost replacement. To have this change approved, the project manager submits a change request that contains which of the following?
A PM is reviewing bids from vendors and has a question.
Which of the following documents should the PM use to obtain a response?
Before a team can start on a sprint, they will need to:
Which of the following documents serves the primary purpose of requesting details about a vendor’s capabilities?
A resource is assigned to two projects with two scheduled tasks that complete at the same time.
This is known as: